Full-depth slip-form installation
Trench / Slip-Form Curb
Trench curb is full-depth, slip-form concrete curb installed into a prepared excavation along the pavement edge. We saw-cut the asphalt, remove the cut strip and trench with our Caterpillar skid steer before our curb machine forms the continuous curb in place.

The North Coast method
Overpave
We ask the paving contractor to overpave approximately 6 inches beyond the planned curb line.
Lay out
Mark the intended face-of-curb line for the curb machine to follow. Then measure approximately 1½ inches behind that face line to mark a separate saw-cut line, following the approved layout.
Saw-cut
Cut the asphalt along the marked line.
Remove
Take out the cut asphalt and prepare the opening.
Trench
Excavate with a trencher mounted to our Caterpillar skid steer, to the required curb detail and grade.
Install
Feed concrete from the ready-mix truck into our curb machine, which forms the continuous curb, then finish and protect the work.
An alternative to precast
Why offer trench curb?
When the approved design permits it, trench curb can replace individual precast sections—often reducing material handling, coordination, installation time and cost. The curb is formed continuously on site, with its full depth extending into the prepared trench.
Preparing the trench



Actual NORCO jobsite footage
Before the curb is placed
The visible face-of-curb line guides our curb machine. The asphalt is saw-cut approximately 1½ inches behind that line, the cut strip is removed, and our skid-steer trencher excavates the channel for the full-depth curb.
Actual NORCO jobsite footage
Watch the curb take shape
On this job, ready-mix concrete feeds into the hopper of NORCO’s gray curb machine. As the machine advances beside the pavement, it forms a continuous curb in the prepared trench.
Overall depth and exposed height
Understanding the curb profile
An 18-inch trench-curb profile describes the overall curb section. Part of that section extends into the trench; the exposed height, or reveal, is measured above the finished pavement.
NORCO has also installed 24-inch trench curb. These are examples of completed work, not a standard depth for every project. The approved plans and site grades set the required curb depth and finished reveal.
What happens below the curb?
These diagrams explain the two methods. The approved curb detail sets the dimensions, grade and installation requirements for the job.